According to the Interim Measures for Environmental Protection Acceptance of Completion of Construction Projects, the Monitoring Report on Environmental Protection Acceptance of Completion of 17 million m2 Double-coated CTP Plate Intelligent Production Line Project is hereby publicized as follows:

 

Project Name: Construction Site of

Double-coated CTP Plate Intelligent Production Line Project with Annual Output of 17 million m2: construction unit

on the south side of science road, dazhou recycled metal recycling industry agglomeration area, changge city: Henan huida yintong technology co., ltd.

publicity content: acceptance monitoring report and acceptance opinions. please refer to annex

publicity time: June 12, 2021-July 12, 2021 (20 working days in total)

publicity period. if you have any objection to the above publicity content, please give feedback in writing. Individuals must sign their real names and units must affix their official seals.

Contact Information: Gu Junwei 18937499788

 